Dandot Cement says that its on-going upgrade to its Lahore cement plant reached 60% completion during the fourth quarter of the 2023 financial year, which ended on 30 June 2023. The project remains scheduled for completion in July 2023. Pakistan Company News has reported that the producer has taken delivery of new equipment, completed civil construction work, handed over the site to its engineering contractor, completed 75% of mechanical erection and conducted some tests. The producer awarded a new contract for installation of remaining portions of its control systems to an Uzbekistan-based contractor. Complete sections of the project include the plant’s captive solar power plant.

Dandot Cement has made total investments worth US$12.3m in the project.